EVNGENCO1 highly focuses on ensuring safe and efficient operation of plants

To meet the increased demand for electricity consumption compared to plan, EVNGENCO1 has closely followed the direction of the Ministry of Industry and Trade and EVN to implement solutions to ensure electricity supply in the 2024 dry season.

In February 2024, the frequency of water returning to EVNGENCO1's hydropower reservoirs in the Central Highlands - South Central region generally follows the plan of the Ministry of Industry and Trade, while the frequency of water returning to hydropower reservoirs in the North Central region is poor. than. The fuel supply for thermal power plants meets operating needs and maintains reserve volumes according to regulations. EVNGENCO1 has operated basic plants stably, meeting the mobilization needs of the national power system, and at the same time worked with local units to have economical and effective water supply plans. as a basis to provide enough water to serve the needs of downstream areas until the end of the dry season.

As a result, in February 2024, EVNGENCO1 produced 1.82 billion kWh, reaching 81.7% of the assigned output plan. Among them, some plants exceeded their assigned output such as Nghi Son 1 Thermal Power Plant (131%), Dai Ninh Hydropower Plant (114.7%).

Nghi Son 1 Thermal Power Plant exceeded the planned electricity output delivered in February

Regarding construction investment, construction investment projects are being implemented by the Corporation according to the assigned schedule. By the end of February, the volume of construction investment implementation reached 38.2% and the disbursement value reached 39.2% of the 2024 plan (including disbursement value for the implementation value of previous years).

In addition, digital transformation continues to be actively implemented by EVNGENCO1 with the goal of becoming a digital enterprise by 2025. Environmental protection is emphasized and many strict and effective measures are implemented.

On the occasion of Lunar New Year 2024 (Tet Holiday), EVNGENCO1 and its units have implemented many social security activities in their operating areas, with a focus on gift giving and support programs for people in difficult circumstances to celebrate the Tet Holiday. In particular, hydropower units of plants belonging to Song Tranh Hydropower Company, Dong Nai Hydropower Company etc. have actively implemented annual activities of stocking fish fingerlings to regenerate aquatic resources in hydropower reservoirs, contributing to creating biodiversity for local people.

Leaders of EVNGENCO1 visited, encouraged employees and worked with units on power production in the dry season of 2024

In March 2024, EVNGENCO1 is highly focused on ensuring the safe and efficient operation of plants, completing the assigned power output of 3.17 billion kWh, closely following the Directive on implementing solutions Ensuring electricity supply in 2024 and following years. In particular, thermal power plants ensure availability, reliability, and maintain good coal reserves; Hydropower plants comply with the Inter-Reservoir Operation Procedure, ensuring safety, efficiency, savings and optimization of water resources; carry out maintenance and repair work according to plan.

Construction investment, digital transformation and other works will still be implemented by EVNGENCO1 as planned, maintaining sustainability and stability of production activities throughout the Corporation.